Upgrades to TTC Emergency Service Buildings


Replacing the diesel generators with natural gas generators
Effective November 2024 until Q3 2025 

As part of the TTC’s commitment to modernization, the diesel generator at 4 Glenayr Road, 2 Church Avenue, and 710 Birchmount Road will be replaced with a natural gas generator.

Construction on the generators will run over the following dates:


 Address  Start Date  End Date
 4 Glenayr Road  November 11, 2024  Q2, 2025
 2 Church Avenue  January 5, 2025  Q2, 2025
 710 Birchmount Road   February 23, 2025  Q3, 2025

 

Work Area
The work will take place within TTC property.

Access
Vehicular and pedestrian access on Glenayr Road will not be impacted.

Work hours

Construction activity will take place between 7 a.m. and 4 p.m., Monday to Friday. Some noise is expected during construction.

 

Thank you for your patience as we work to improve transit in Toronto. 

 

For further information:

Clive Scott, Senior Community Liaison,
437-219-5174,