Kipling Station - Hydro One Work


Hydro One Construction at North and South Parking Lots
Effective June 9, 2025 until Q4 2025 

Timeline: As early as June 9, 2025 to end of 2025*

*Content / timeline accurate during this communication and is subject to weather and unforeseen events

 

What is happening and why?

Hydro One is upgrading the power line across a 6.5 km transmission corridor, including the Kipling Station area, to improve electricity on this corridor. The project involves temporarily relocating the existing power line, connecting the new power line to the newly installed structures to support it, and removing the existing power line after the new power line is operational.

 

This construction work is happening in Kipling Station’s north and south parking lots and the immediate surroundings.

 

What to expect

  • Parking: North and south parking lots will remain open, but there will be a temporary reduction of parking spots in both lots. Approximately 50 parking spots will be permanently removed from the south parking lot.
  • Pedestrian walkway: Temporary closure of some parts of the pedestrian walkway. Detour signage will be installed.
  • Bike racks and lockers: The bike racks and lockers at the north and south parking lots will be temporarily unavailable.
  • Some noise and vibration should be expected.
  • Construction hoarding, vehicles, and crew will be present at the site.

Work hours

This work is expected to occur Monday to Friday between 7 a.m. and 7 p.m. Some work on weekends and overnight may be required.

 

TTC service

TTC services will not be affected by this construction.

 

For further information:

Reka Sivarajah, Senior Community Liaison, 437-994-6317, Reka.Sivarajah@ttc.ca