Bid irregularities
In accordance with the Commission's Procurement Policy, Section 8.0, the following is a list of common Bid Irregularities that may be contained in a Bid. This list identifies the type of irregularity and the action to be taken by the Commission, whether the Bid is considered compliant or non-compliant. This list is not exhaustive of all irregularities that may be contained in a Bid and may be amended by the TTC, at its sole discretion, from time to time.
Last Updated: Monday, November 26, 2007
| Number | 
             Irregularity  | 
            
             Response  | 
        
|---|---|---|
| 
             1  | 
            
             Late Bids.  | 
            
             Automatic rejection and not read publicly.  | 
        
| 
             2  | 
            
             Insufficient financial security (No deposit or bid bond or insufficient deposit or bid bond).  | 
            
             Automatic rejection.  | 
        
| 
             3  | 
            
             Incomplete Bids (Part bids - all items not bid).  | 
            
             Automatic rejection, unless otherwise provided in the Request.  | 
        
| 
             4  | 
            
             Exceptions (as defined in the Commission's Procurement Policy).  | 
            
             Automatic rejection.  | 
        
| 
             5  | 
            
             Qualifications (as defined in the Commission's Procurement Policy)  | 
            
             Acceptable.  | 
        
| 
             6  | 
            
             Bids received on documents other than those provided by the Commission.  | 
            
             Automatic rejection, unless the information provided does not materially affect the substance or form of the Request, as determined at the sole discretion of the Head - Materials and Procurement).  | 
        
| 
             7  | 
            
             Bids containing errors.  | 
            
             Automatic rejection, unless the errors do not materially affect the Bid, as determined at the sole discretion of the Head - Materials and Procurement.  | 
        
| 
             8  | 
            
             Failure to sign Agreement to Bond, Bid Bond Bid Document (i.e. Form of Tender/Proposal).  | 
            
             Automatic rejection.  | 
        
| 
             9  | 
            
             Erasures, overwriting, strike-outs, or failure to initial changes made on Bid.  | 
            
             Automatic rejection, unless it does not materially affect the Bid, as determined at the sole discretion of the Head - Materials and Procurement.  | 
        
| 
             10  | 
            
             Discrepancies between the written price and the numerical price  | 
            
             Automatic rejection.  | 
        
| 
             11  | 
            
             Failure to acknowledge in the Bid that all addenda form part of the submission in the Bid.  | 
            
             Automatic rejection, unless the failure would not have a material impact on the intent of the contract, as determined at the sole discretion of the Head - Materials and Procurement.  | 
        
| 
             12  | 
            
             Discrepancies between the written price and the numerical price  | 
            
             Automatic rejection, if Request specifically requires optional pricing to be submitted. If optional pricing is not a mandatory requirement, failure to provide optional pricing is acceptable.  | 
        
| 
             13  | 
            
             Requested submission requirements not included in the Bid, in whole or in part.  | 
            
             Automatic rejection if information was a mandatory requirement in the Request. If information was not mandatory, any missing information must be assessed at the sole discretion of the Head - Materials and Procurement to determine whether the missing information materially affects the Bid.  | 
        
| 
             14  | 
            
             Failure of a Bidder to identify itself on the Bid.  | 
            
             Automatic rejection.  | 
        
| 
             15  | 
            
             Mathematical errors.  | 
            
             Automatic rejection unless otherwise provided in the Request.  | 
        
| 
             16  | 
            
             Agreement to Bond not signed by both the Contractor / Company and the Surety; or Agreement to Provide Irrevocable Letter of credit not signed by the Financial Institution.  | 
            
             Automatic Rejection  |