Bloor-Yonge Station Capacity Improvements


Contact Us

If you are interested in receiving updates about this project, please sign-up to our email list. If you require any information about the project, please email blooryongeproject@ttc.ca or call 416-472-2524.

 

Background

Bloor-Yonge Station is located at the intersection of Yonge and Bloor streets and is the busiest station on the TTC. The original station opened in 1954 and now requires expansion and modernization to accommodate future TTC ridership and neighbourhood density. Line 1 and 2 passenger platforms are already experiencing crowding and queuing during both the morning and evening rush hours.  Bloor-Yonge is an interchange subway station and a significant transfer point that provides access to both Line 1 and Line 2. In 2019, Line 1 had average daily weekday ridership of more than 825,000 riders, making it one of the busiest lines in North America. The TTC expects ridership to experience significant growth both from the increasing population in the GTA and from transit expansion, including the northern extension of Line 1 to Richmond Hill Centre, the opening of the Eglinton Crosstown LRT  and the future Ontario Line On the platform for Bloor-Yonge Station. Subway trains have arrived on each side of the platform. The left side train is still closed and passengers are waiting to board. The right side train is open and passengers are exiting the train.


What we’re doing

Bloor-Yonge Station will be undergoing a design retrofit and significant expansion to meet both current and future ridership demand. The Bloor-Yonge Station project includes the construction of a new Line 2 passenger platform and the expansion of both Line 1 passenger platforms, enhancements to the concourse level, entrances, exits and improved accessibility features.

Artist’s rendering of the future Bloor-Yonge Station expanded Line 1 Southbound platform. Design subject to change.

Artist’s rendering of the future Bloor-Yonge Station expanded Line 1 Southbound platform. Design subject to change.

The improvements Bloor-Yonge Station include:
  • Expansion of Line 1 northbound and southbound platforms
  • A new second platform to enhance capacity for eastbound passengers on Line 2
  • Line 2 original platform reconfiguration to enhance capacity for westbound passengers
  • A new barrier-free entrance
  • A new exit to Bloor Street
  • New escalators, elevators and stairs
  • New public art and station finishes
  • One new electrical substation to power new and existing areas of the station and ventilation systems
  • New fan plants to improve ventilation
  • Utility upgrades

Upon project completion, platform edge doors will be installed and operational on Line 1 at Bloor-Yonge station, as the Line 1 Automatic Train Control (ATC) signal system is already in place.

Infrastructure will be installed for Line 2 at Bloor Yonge Station to enable future platform edge doors. Platform Edge Doors on Line 2 will be possible once the full Line 2 Automatic Train Control (ATC) signal system is installed.

The Bloor-Yonge Station Capacity Improvements project is being designed to enhance accessibility and safety in accordance with the Accessibility for Ontarians with Disabilities Act, 2005 (AODA) and the Ontario Building Code.

 Artist’s rendering of the future Bloor-Yonge Station expanded Line 1 Northbound platform. Design subject to change.

Artist’s rendering of the future Bloor-Yonge Station expanded Line 1 Northbound platform. Design subject to change.

Artist’s rendering of the new Bloor-Yonge Station Line 2 eastbound platform. Design subject to change.

Artist’s rendering of the new Bloor-Yonge Station Line 2 eastbound platform. Design subject to change.

Artist’s rendering of the reconfigured Bloor-Yonge Station Line 2 westbound platform. Design subject to change.

Artist’s rendering of the reconfigured Bloor-Yonge Station Line 2 westbound platform. Design subject to change. 

Accessibility and Ridership

The design includes additional escalators, elevators and barrier-free entrances, which means more station accessibility and an enhanced and inclusive customer experience. 

Elevator in Bloor-Yonge Station to Line 1 Northbound, and Like 2 Eastbound and Westbound. The stainless steel elevator is to the left with 6 Presto turnstiles to the left. One person is going through the turnstile. The wall is orange tile in the background.

By the Numbers

2019

  • Line 1 Ridership: 210,000 per day, or 65,000,000 annually.
  • Line 2 Ridership: 180,000 per day, or 55,000,000 annually.
  • Unique customers to Bloor-Yonge Station: 220,000 per day or 67,000,000 annually
  • Morning rush hour ridership: 26,000

2029 (Anticipated 2029 Ridership)

  • Line 1 Ridership: 270,000 per day, or 83,000,000 annually.
  • Line 2 Ridership: 225,000 per day, or 69,000,000 annually.
  • Unique customers to Bloor-Yonge Station: 280,000 per day or 86,000,000 annually
  • Morning rush hour ridership: 31,000

What's New

  • The TTC has removed the former carwash at 830 Church Street beside the Toronto Reference Library to build a future fan building to enhance air circulation at the station.  
  • Advanced utility relocation work on Bloor Street East is scheduled to begin in Q1 2024.
  • Major construction is planned to begin in 2025.
  • Specific timelines will be confirmed after engineering is completed and a contract is awarded.

Project Updates

  • Project demolition work at 830 Church Street, 40/42 Hayden Street, and 81 Bloor Street East was completed successfully in Q4 2023. Project utility work was initiated in January 2024 and includes hydro relocation work on the north side of Bloor Street East and sewer relocation work on the south side of Bloor Street East, between Yonge Street and Park Road. The hydro work on the north side of Bloor Street will shift to the south side of Bloor, as well as along the road between the north and south side of Bloor Street East. The work is being carried out to accommodate the significant station expansion to meet both current and future ridership demand and is scheduled to be completed by Q4 of 2024.
  • The TTC has released a Request for Proposals (RFP) for the Bloor-Yonge Capacity Improvements project (BYCI). Three teams were shortlisted through a Request for Pre-qualification (RFPQ) process conducted last year and are now invited to respond to the RFP. For more information, please see the news release.
  • This project is at 30% conceptual design or Stage Gate 3.
  • Stage Gate 3 or approximately 30% design was approved by the TTC Board in December 2021. The approval of Stage Gate 3 established the overall project performance baseline definition for project scope, schedule and cost, as well as determined the best project delivery strategy.

Funding

The total cost for the Bloor-Yonge Station Capacity Improvements project is currently estimated at $1.5 billion, to be funded equally by the City of Toronto, the Province and the Federal government. City Council approved its funding share during the 2020 Budget process by allocating $500 million in new funding from the City Building Fund in the TTC’s 2020-2029 Approved Capital Budget and Plan. The City’s funding enables the TTC to begin the necessary planning and preparatory work for this project.

Presentations

Construction Notices

Please go to the construction notices page to see the latest updates.

Reports

City Council Reports

TTC Board Reports

Project Community Office

The TTC has opened the project community office directly south of Bloor-Yonge Station, at 25 Hayden Street.

Dedicated Community Relations team members are available to discuss the project, answer questions, and make sure everyone is kept in the loop. Office hours are by appointment, please reach out by phone or email.


Contact us

If you are interested in receiving updates about this project, please sign-up to our email list. If you require any information about the project, please email blooryongeproject@ttc.ca or call 416-472-2524.

 

X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm