Project Overview

Easier Access

The TTC's Easier Access Program is making subway stations accessible. Two new elevators are being built at Spadina Station (Line 1) as part of the Easier Access Program. Construction is ongoing, and elevators are scheduled to be in service by the end of 2026. 

Cross-section image of station elevators

What we are doing and why

 

The TTC is building two new elevators to create a barrier-free path connecting the subway platform level on Line 1 to the underground pedestrian walkway leading to Spadina Station Line 2, the streetcar platform, the bus terminal, and the street-level entrances/exits.

 

The Easier Access improvements will include:

  • Two new elevators
  • Improved signage
  • CCTV – Security cameras inside the station

Work hours

Work will typically take place Monday to Friday between 7 a.m. and 7 p.m. Some work on weekends and overnight may be required. 

TTC service

 

Subway service at the station will be maintained throughout construction. 

 

Thank you for your patience as we work to improve Spadina Station (Line 1).

 

Project Documents

Community Presentation - September 2025

 

 

Easier Access Program

  • Program overview

    TTC’s Easier Access Program will make all subway stations accessible to everyone, regardless of their level of mobility. Today, more than half of our stations are accessible to people with disabilities. Learn more about the complete schedule.

  • TTC is making progress towards its goal of making all of its stations accessible as part of the Easier Access program.

    Stations

    Complete in

    Donlands 2024
    Castle Frank 2024
    Glencairn 2024
    College 2025
    Lawrence 2025
    Greenwood 2025
    Christie 2025
    Summerhill 2025
    High Park 2025
    Museum 2025
    Rosedale 2025
    Warden 2025
    Spadina 2026
    Old Mill 2026
    King 2026
    Islington 2026

     

    All schedules are subject to change.

Contact us

If you are interested in receiving updates about this project, please email your contact information to the project's Community Liaison Officer.

Please be sure to include your name, address (including city and postal code), phone number and email address. Also, please let us know how you prefer to be contacted – by email, regular mail or both.

Bethany Wong
Senior Community Liaison Officer
Bethany.Wong@ttc.ca
647-459-6426

Construction notices

Active construction notices related to this project include:
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm