TTC continues key track renewal work on Line 2 this past weekend
TTC crews carried out important track work this past Sunday morning during the suspension of subway service on Line 2 Bloor-Danforth between Jane and Ossington stations.
Crews removed and replaced a rail joint, helping to improve reliability and keep trains running safely. CCTV cameras were also installed in the Keele Yard, near Keele Station, to improve security and provide additional monitoring of out-of-service trains.
This work is part of the TTC’s ongoing investment in maintaining and modernizing one of North America’s busiest subway systems. Track renewal projects help provide a smoother ride, reduce infrastructure-related delays, and improve long-term safety and service reliability for customers.
Monday to Friday – Early nightly subway closures on Line 1 between Lawrence West and St Andrew stations
From Mon., Nov. 2, to Fri., Nov. 6, subway service on Line 1 Yonge-University between Lawrence West and St Andrew stations will end at 11:59 p.m. each night for planned track and infrastructure improvements. During the closure, crews will continue replacing rail components in areas where reduced speed zones are in effect, helping restore normal train speeds through this section of the line by late November. Crews will also upgrade communication and safety equipment at stations and at track level, install new advertising signage, and carry out structural repairs near Dupont Station to support ongoing maintenance and reliability of the subway.
Shuttle buses will operate between Lawrence West and St George stations only. There will be no shuttle buses between St George and St Andrew stations. Customers can take Line 2 to Bloor-Yonge Station to connect to Line 1. Customers can also use east and west bus and streetcar routes to travel through the downtown core. Wheel-Trans service will be available for any customer requiring assistance. Customers can speak with TTC staff for assistance.
Glencairn, Dupont, Museum, Queens Park, St Patrick and Osgoode stations will be closed, as well as the Heath Street entrance at St Clair West Station, and the Kendal Avenue entrance at Spadina Station. All other subway stations will remain open for customers to load PRESTO cards, purchase PRESTO Tickets, and connect to surface routes.
While the TTC does most subway maintenance after service each night, it continues to require weekend and early weeknight closures to complete critical infrastructure and state-of-good-repair work.
The TTC is committed to keeping customers informed about work and events that impact service, as well as alternate route options. For the most up-to-date information, follow @TTCNotices on X or sign up for eAlerts. Customers can also use Transit app to plan their journey in real-time.