Construction at Castle Frank Station began in late Fall 2021 and is scheduled to be completed in 2024.

castle-frank-section

Cross section image of station elevators

This work will include:

  • Two new elevators, one to each passenger platform
  • Improved signage
  • CCTV - security cameras along the accessible pathway
  • Accessible sliding doors at the main entrance

What to expect:

Current phase of work includes activities related to the new elevator shafts, located near the existing station entrance. No trees are planned to be removed.

 Work hours

Work is generally taking place Monday to Friday between 7 a.m. and 7 p.m. Some work on weekends between 9 a.m. and 5 p.m. may be required to expedite the project.

TTC service

Access to the station, bus and subway service will be maintained throughout construction.

  

For further information:

Paul Tran
Community Liaison
647-461-5133
paul.tran@ttc.ca