The Great Big Pour at VMC

July 6, 2015

The next stage of construction at the TYSSE Vaughan Metropolitan Centre Station involved pouring a massive amount of concrete to fill the main entrance ring for the station. Because of the magnitude of the pour, two concrete plants, with a third on standby, were required to produce the concrete.

At 3:30 a.m. on Saturday, July 4, 2015 the concrete pour began. Concrete trucks arrived every five minutes and construction crews worked in 10 hour shifts, with two crews placing the concrete in different sections. Concrete was placed at a rate of 70-100 cubic metres per hour with a total of 2250 cubic metres poured! The great big pour finished on Sunday, July 5, 2015 at 4:00 a.m.

Main entrance ring and x-beam re-bar and formwork complete and ready for concrete pour.

Main entrance ring and x-beam re-bar and formwork complete and ready for concrete pour.

VMC entrance ring concrete pour with two concrete pumps and crews.

VMC entrance ring concrete pour with two concrete pumps and crews.

One of two pumper trucks pouring the entrance ring.

One of two pumper trucks pouring the entrance ring.

24 hour pour of main entrance ring complete - looking northeast.

24 hour pour of main entrance ring complete.

24 hour pour of main entrance ring complete - looking northwest.

24 hour pour of main entrance ring complete.

Bus Route Changes

TTC Bus

Review the new changes to bus routes in the area to connect to the new subway extension.

Read about it here!

Need Information

To contact us for information about the project:

Call 416-393-4636 (INFO) automated information available 24 hours daily.

Contact the Project

Photo Gallery

Check out the latest construction photos and project YouTube videos.

Click here to view the Photo Gallery.

Project News