While
every effort is made to ensure the accuracy of the contents of this site, users
should be aware that due to circumstances beyond our control, it may be
necessary to change the text of documents posted here and therefore no
responsibility will be accepted by the Toronto Transit Commission for
discrepancies which may occur between documents contained on this site and the
formal hardcopy versions presented to the Commission.
If it is necessary to rely on the accuracy of Commission documents the Office
of the General Secretary should be contacted at 393-3698 to obtain a certifed
copy. ONLY HARDCOPY RECORDS CERTIFIED BY THE GENERAL
SECRETARY WILL BE DEEMED TO BE OFFICIAL.
Form Revised: February 2005
TORONTO
TRANSIT COMMISSION
REPORT NO.
MEETING DATE: July 11, 2007
SUBJECT: TRANSIT CITY LIGHT RAIL PLAN
-
IMPLEMENTATION WORK PLAN UPDATE
RECOMMENDATIONS
It is recommended that the
Commission:
1.
Receive this report, noting that, in response to the
June 15, 2007 provincial announcement of the MoveOntario 2020 transit funding program, which calls for the start
of construction of new rapid transit lines by 2008, TTC staff are updating
their work plan for the implementation of the Transit City Light Rail Plan to accelerate the previously-indicated
2010 start-date, through measures including:
·
creation of a designated inter-departmental Transit
City Project Team, with increased staffing, to oversee an expedited implementation
of the Plan;
·
consolidating both planning/approval studies and engineering
design work into single consulting contracts for each specific light rail
corridor;
·
consideration of alternate project delivery methods
such as design-build and alternative financing and procurement;
·
an accelerated process for community input and
political decision-making;
·
immediate acquisition of property for light rail
vehicle maintenance yards in advance of final decisions regarding approvals and
funding for the light rail lines;
·
increasing the order for new light rail vehicles so
that, in addition to acquiring new light rail vehicles to replace the TTC’s
aging fleet of streetcars, there will also be delivery of sufficient new light
rail vehicles to operate the selected Transit
City lines beginning in 2012;
·
developing a communications plan to inform TTC
customers and Toronto residents about the Transit
City Light Rail Plan, its ongoing activities, status, and progress on a
regular basis;
2.
Note that:
·
this accelerated approach requires that the City, the
GTTA, and Provincial and Federal agencies accelerate their normal review or approval
time frames for funding and environmental assessments, to allow for the early
implementation of the light rail lines;
·
TTC staff are continuing the preliminary fieldwork and
site investigations of the Transit City
light rail lines, and are now working on the Eglinton-Crosstown corridor. This
corridor, together with the previously-investigated Etobicoke-Finch West and
Sheppard East corridors, are currently the leading candidates for early construction.
They will achieve significant reach for Toronto’s rapid transit network, bring
premium quality service to areas which currently do not have it, achieve strong
ridership levels, and offer significant potential in terms of inter-regional rapid
transit connectivity, including Pearson Airport;
·
TTC staff will be providing an overview of the Transit City Light Rail Plan at the
forthcoming July 27, 2007 meeting of the GTTA Board;
·
The TTC’s immediate priority for the north Yonge
Street corridor is to deliver significant service improvements through the construction
of the Yonge Street Bus Rapid Transit facility. This should proceed immediately
in order to improve the quality of service for the tens of thousands of
customers who travel in this corridor daily, given that it will take many years
to complete the extension of the Yonge Subway to Highway 7, and given that the
busway is an excellent, cost-effective, near-term measure that will build
ridership in this corridor in the interim period. Any proposal to extend the
Yonge Street subway north from Finch Station should be assessed and prioritized
by the GTTA as part of their forthcoming Greater Toronto Area and Hamilton (GTAH)
Regional Transportation Plan, and it should not delay the more-immediate
significant improvement that would result from early implementation of the
busway;
·
staff will be developing a communications plan to
inform TTC customers and Toronto residents about the Transit City plan, its ongoing activities, status, and progress on
a regular basis; and
3.
Forward this report to the City of Toronto, the
Greater Toronto Transit Authority, the Province of Ontario, and the Government
of Canada.
FUNDING
On June 15, 2007, the Province of
Ontario announced funding of $17.5 billion for the implementation of the MoveOntario 2020 GTAH rapid transit program
over the next 12 years. MoveOntario
2020 includes funding for the TTC-City of Toronto Transit City Light Rail Plan whose total cost is
estimated at $6.0 billion.
This current report has no effect
on the TTC’s capital or operating budgets. Funds for the necessary preparatory planning/EA
work in 2007 were included in the TTC’s 2007-2011
Capital Program, under 3.9 Buildings and Structures – Environmental
Assessments for a BRT/LRT Network (Category – Improvement) as outlined on pages
992 e1-e2, approved by City of Toronto Council on March 7, 2007.
Funding for additional staff
resources, and capital for the acquisition of maintenance yard sites, planning/design
consulting contracts, and other activities related to the implementation of the
Transit City Light Rail Plan, will be
included in the 2008-2012 Capital Budget, which will be presented to the
Commission for approval in the fall.
BACKGROUND
At its meeting of June 13, 2007,
the Commission approved a report entitled, Transit City Light
Rail Plan – Implementation Work Plan, which outlined the activities
being undertaken to implement the Transit
City Light Rail Plan. That report presented an “aggressive and ambitious”
work plan to allow for the start of construction on at least one of the light
rail lines by 2010.
On June 15, 2007, the
Province of Ontario announced the MoveOntario
2020 funding program for the implementation of 52 rapid transit initiatives
in the GTAH over the next 12 years. MoveOntario
2020 includes funding for all of the light rail lines in the Transit City Light Rail Plan, as
well as for extensions of the Spadina and Yonge subway lines into York Region,
significant upgrades to GO Rail service, and bus and light rail transit rights-of-way
in a number of other municipalities in the GTAH.
Following the release
of MoveOntario 2020, TTC staff were directed
to revisit their original implementation work plan to identify ways of
accelerating the plan to more-closely match the 12-year time frame contained in
the Provincial plan, including the feasibility of starting construction on one
of the light rail lines as early as 2008.
This report responds to
that directive.
DISCUSSION
Provincial MoveOntario
2020 Announcement
The Provincial MoveOntario 2020 funding program
contains 52 rapid transit projects for implementation in the GTAH over the next
12 years. The program represents a vision of dramatically-improved transit
services throughout the GTAH in a very short time frame. It includes all seven
of the Transit City Light Rail Plan lines,
an extension of the Scarborough RT, and extensions of the Spadina and
Yonge subway lines into York Region. The
City of Toronto will also benefit from the extensive upgrades being proposed
for GO Rail services.
The TTC has a long history of
operating inter-regional services between Toronto and its neighbouring
municipalities, dating back to 1930. Similarly, the TTC has, for many years,
worked closely and cooperatively with all of its neighbouring municipal transit
agencies and GO Transit in the design and planning of inter-regional transit
services. The TTC participated in the Ministry of Transportation’s Fare
Integration and Service Coordination initiatives of the 1990’s, as well as in
the Greater Toronto Services Board’s development of a transportation plan for
the GTA. The TTC expects to continue to work closely with both the
Greater Toronto Transportation Authority (GTTA) and the GTAH
municipalities in the development of a new, long-term regional transportation
plan for the GTAH.
The GTTA will play a key role in
transforming the visionary MoveOntario
2020 funding program into a fully-integrated multi-modal regional
transportation plan for implementation throughout the GTAH. Projects which have
significant inter-regional aspects or implications for inter-regional travel must
be dealt with in this GTTA inter‑regional transportation plan, to ensure
consistency of treatment and analysis, and to allow for a systematic approach
to prioritization. In contrast, projects whose main purpose is to provide local
service and/or to support specific municipal/official plan land use and
development objectives should be able to proceed in parallel with the GTTA’s
comprehensive GTAH-wide transportation plan.
Priorities for Implementation of Transit City Light Rail
Plan
At this time, the TTC-City of
Toronto are starting to implement the Transit
City Light Rail Plan. While the Plan
has significant potential and expandability to meet inter-regional travel
demands between Toronto and its neighbours, it is designed largely to support
the explicitly pro-transit transportation policies and local
transit-corridor-oriented development and intensification objectives of
Toronto’s Official Plan.
The Transit City Plan’s genesis
was to provide excellent local transit service in existing established major
transit corridors, and to provide improved access to areas designated for new high‑density
development. The Plan’s underlying
purpose was to operationalize the Official Plan’s objective of making
transit a much-more attractive and viable travel option for people travelling
in Toronto and, in so doing, reduce Toronto’s dependence on the automobile and
the associated congestion, pollution, and inefficient land uses. The Plan can, and should, be implemented
quickly and aggressively, in parallel with the development of the GTTA’s GTAH-wide
transportation plan.
All seven light rail lines
contained in the Plan will be strong-performing
routes when implemented, either because they already have a very strong base of
existing ridership, or because they serve areas which have been designated for,
or are undergoing intensification and re-urbanization, or both. As previously
described, the lines were initially screened through these preliminary measures:
·
Application
of corridor selection and evaluation criteria including status in the Official
Plan, service to priority neighbourhoods,
existing and future ridership, and rapid transit coverage and reach throughout
the city;
·
Identification
of general routing alignments, including
physical feasibility and major required structures, and approximate location of
terminals and transfer connections;
·
Projected
corridor ridership, taking into account major ridership generators and
destinations;
·
Projected
service levels and designs, including identification of vehicle requirements;
·
Identification
of inter-regional connectivity potential, including connections with GO Transit.
Preliminary fieldwork, alignment reviews, and structural
requirements have already been completed for the Etobicoke-Finch West and
Sheppard East light rail lines, and this work is about to start for the
Eglinton-Crosstown light rail line. At this time, TTC staff believe that these
three lines are strong candidates for early implementation because they will achieve significant
reach for Toronto’s rapid transit network, bring premium quality service to
areas which currently do not have it, achieve strong ridership levels, and
offer significant potential in terms of inter-regional rapid transit
connectivity, including Pearson Airport, an international gateway.
Recently, TTC staff have been
asked to present a more-formal and structured evaluation and ranking of the
seven light rail lines in the Plan.
Staff will present such an evaluation in one of the forthcoming reports
addressing details of the implementation of the Plan. Due to the resources required of both TTC and consultants, it
will be prudent and more efficient to ultimately focus on one light rail line to
commence construction in 2008, with planned commencement of other lines in the
following years.
Improving Transit Service in the
North Yonge Street Corridor
The Yonge Subway line is the
busiest service the TTC operates and has been operating close to, or at
capacity for many years. For this reason, both the ridership and the operation
of the line is monitored closely and has been the subject of a number of
detailed evaluations.
The capacity constraint on the
line occurs southbound from Bloor Station between 8:00am and 9:00am on
weekday mornings. Twenty-eight trains are scheduled to operate through this
“peak load point” between 8:00am and 9:00am, and this is the maximum practical
capacity that can be operated reliably, given the current signalling system and
the physical design of the key stations on the line (Bloor-Yonge and the
terminal stations). Ridership during the peak hour is currently as high as it
has ever been, at 29,000 passengers per hour in the peak direction, with
crowding on trains being close to the applicable loading standards for most of the
peak hour. It is a regular occurrence at Bloor Station that passengers have to wait
for a number of trains before they are able to board.
Owing in part to this capacity
constraint, ridership on the Yonge Subway line at peak times into the downtown
has remained relatively stable over the past 20 years. Growth in peak-transit
travel into the downtown area has been primarily accommodated through
expansions in GO Rail services. In addition, the large increase in
residential development close to the core, facilitating live-work lifestyles,
has helped to moderate the need for more transit capacity into the downtown
area.
The Yonge Subway line to Highway
7 should be pursued as part of a broader regional implementation plan that will
ensure that the line will be able to accommodate additional ridership demand
which would be generated by an extension. In particular, the following factors
need to be considered:
·
completion of the already-committed extension of the
Spadina Subway line north to the Vaughan Corporate Centre in York Region, in
order to give travellers from York Region an alternative rapid transit
option into Toronto’s central area;
·
potential to significantly expand GO Rail services on
the Richmond Hill and Bradford lines, also as a means of diverting
longer-distance passengers from the north onto GO Rail services;
·
increasing the capacity of the Yonge Subway line
through the implementation of the already-planned purchase of higher-capacity
trains and through the implementation of the already-planned “Automatic Train
Control” signalling system which will allow increases in the frequency of train
operation and, thus, capacity.
However, action must be taken now
to improve the quality of service experienced by the approximately tens of
thousands of passengers who currently travel by transit each day in the north
Yonge Street corridor, north of Finch subway station. Transit services in
this corridor, which are provided by the TTC, York Region Transit, VIVA, GO
Transit, and Brampton Transit, operate, for all intents and purposes, in mixed
traffic. The customers of these services experience unreliable and slow service
which is typical of mixed-traffic operation. The planning, design, and
construction of a future Yonge Subway extension to Highway 7 will take many years
to complete. In order to provide the service improvements which are required
right now in the north Yonge Street corridor, the TTC intends to continue its
current efforts to implement a bus rapid transit facility in this corridor as
quickly as possible. This is an affordable “quick win” rapid transit
improvement which will benefit large volumes of existing local and
inter-regional transit customers right away and for many years to come. This
joint Toronto-York Region initiative should be continued and implemented,
without any change to the current plans or work arrangements.
Implementation and Timing Issues for the Transit City Plan
The implementation work plan presented
in the June 13, 2007 report presented an ”aggressive and ambitious” schedule
which called for the start of construction of at least one of the light rail
lines by 2010. Accelerating this already-ambitious plan will require actions
not normally undertaken by the TTC, the City of Toronto, or the senior levels
of government. The changes proposed here are far from final, and represent the
most-current discussions on this matter at the time of preparation of this
report.
Transit City Project Team
To implement the Transit City Light Rail Plan in an
accelerated way will require the establishment of an inter-departmental coordinating
group within the TTC, dedicated to the implementation of the plan. The Transit
City Project Team will include transit planners, design engineers, track and
overhead specialists, vehicle engineering experts, tunnel and structure
experts, and individuals with large-project project management expertise. The
huge scale of the Transit City plan –
bigger than any previous system expansion undertaken by the TTC – will require
an increase in staffing to ensure the expeditious implementation of the Plan. Staff will report back on a recommended
organisational structure, a staged approach to staffing the Team, and workforce
and budgetary implications.
Concurrent Seeking of Approvals
and Undertaking Engineering Design Work
Typically, the TTC does not
undertake detailed design work for a planned project until after approvals have
been obtained and funding has been secured. This is done to reduce the
potential for wasting expensive Engineering design work on a project which may not
get approval to proceed. It also avoids potential criticism, during the
approval process, that decisions and commitments have been made before full
public and political support for the project has been confirmed.
In order to expedite
implementation of the Transit City
plan, the TTC will break away from this traditional sequential work pattern
and, instead, undertake detailed engineering design work in advance of project
approvals. This proposed accelerated approach would involve retaining a single
consulting team to undertake both the planning/approvals work of a light rail
line project and the detailed engineering design for the preferred option, both
at the same time.
Alternate Project Delivery
Methods
In order to proceed in the most
expeditious and efficient way, staff are examining the optimum project delivery
method options for each of the lines. A wide range of project delivery methods
will be screened for each line, such as a design-bid-build (TTC traditional
method), design-build, and alternative financing and procurement. It is
possible that one delivery method will be chosen for one line and another for
other lines, depending on several factors such as risk, complexity, etc. The
goal is to choose the best project delivery method for each of the lines that
will result in early completion of the line at the lowest possible cost.
Immediate Acquisition of Property
for an LRT Yard in Advance of Overall Project Approvals
A critical component of the
implementation plan, and a critical-path factor for the opening of the new
light rail lines, is the construction of a light rail vehicle maintenance yard(s)
and facility(ies). It is critical that work begin immediately on the identification
of possible yard locations, property acquisition, and the construction of a
yard/maintenance facility. Staff are
starting work on identifying and assessing possible yard sites with an
expectation of recommending the early acquisition of one or more sites in 2008.
Funding for these acquisitions will be included in the 2008-2012 Capital
Budget.
Increasing the Order for New
Light Rail Vehicles for Operation on Transit City Lines, Beginning in 2012
The current Light Rail Vehicle
acquisition plan calls for the purchase of 204 new light rail vehicles to
replace the current aging streetcar fleet between 2011 and 2018. This
replacement plan includes some additional vehicles for expected growth on the
existing streetcar lines, but does not include any vehicles for use on the new Transit City light rail lines.
To open one or more of the Transit City light rail lines on an
accelerated basis will require that vehicles be added to the current LRV
purchase plan for delivery in time for operation of the lines when they are
completed. Six of the Transit City
light rail lines are expected to require 15 to 20 LRV’s on opening day, and
ridership growth would eventually require between 25 and 35 LRV’s per line. The
seventh line -- Eglinton-Crosstown -- is much longer than the others, and would
need to be opened in stages, likely requiring approximately 20 to 25
LRV’s for each stage. In total, full build-out of the Transit City light rail network is expected to eventually require
approximately 250 additional light rail vehicles.
As part of the 2008-2012 Capital
Budget, the LRV fleet acquisition plan will be adjusted to incorporate the
purchase of additional LRV’s in the early
years of the delivery contract to allow for the operation of new Transit City light rail lines beginning
in 2011 and 2012.
Accelerated Process for Community
Input and Political Decision-Making
Recent transit right-of-way
projects have incorporated extensive community input processes, and extended
time frames for political decision-making. The EA process for transit projects
is being simplified through a new transit “chapter” of the Municipal Class EA process
document, which has recently been endorsed by City Council and which is
expected to be approved by the Minister of the Environment by September. This change
in process will provide municipalities with a wide degree of flexibility with
respect to how much community input they wish to undertake on individual
transit projects.
With City Council’s support, the
time required for community input on the planning and design of transit
projects could be significantly compressed. This does not mean that the
community input process will be less effective. In fact, placing time limits on
input processes could have the effect of quickly focusing attention on critical
elements, which could make for more‑effective community input. TTC staff
will bring forward a proposal for managing community consultation for the light
rail corridor projects, intended to quickly identify and address key community
concerns.
For the approach to be successful,
it will require the endorsement of City Council as a whole, and a commitment of
compliance from each individual Councillor whose ward is affected by such
projects.
Accelerated City, GTTA, Provincial
and Federal Agencies Approval for Funding and Environmental Assessments
Achieving early implementation of
the Transit City light rail lines
will require a commitment by all levels of government to expedite normal
planning, funding, and review processes. The City of Toronto will be required to
respond to a wide-range of planning and technical issues that will need to be
resolved quickly for these projects to proceed on an accelerated basis. To
achieve this, a single point of accountability within the City’s administration
should be identified to address all City concerns and issues with respect to
the accelerated implementation program.
Similarly, GTTA, provincial, and
federal environmental assessment reviews and normal funding processes will need
to be expedited to allow for early implementation of the lines. The Province of
Ontario has strongly supported a streamlined environmental assessment
process including the development of a Municipal Class EA process for transit. Quick
approval of this Municipal Class EA process by the Minister of the
Environment will be an important first step in this accelerated process for
transit.
It is also proposed that a
Transit City Inter-Governmental Facilitation Committee be established, composed
of senior representatives from the City, the GTTA, the Province, and the
Federal Government, to expedite Transit
City-related matters and requirements through their respective
jurisdictions.
Communications Plan
An integral part of the
implementation plan for the Transit City
light rail plan will be a communications plan to regularly inform TTC
passengers and the general public of the overall plan, the public consultation
initiatives as part of the approvals process, the more‑detailed design
work for corridors as they proceed, and construction and line-opening status. A
web site, a newsletter, posters and flyers on TTC vehicles, and regular reports
in the Metro newspaper are being considered for inclusion in the communications
plan.
- - - - - - - - - - - -
July 4, 2007
11-31-80