While every effort is made to ensure the accuracy of the contents of this site, users should be aware that due to circumstances beyond our control, it may be necessary to change the text of documents posted here and therefore no responsibility will be accepted by the Toronto Transit Commission for discrepancies which may occur between documents contained on this site and the formal hardcopy versions presented to the Commission.
If it is necessary to rely on the accuracy of Commission documents the Office of the General Secretary should be contacted at 393-3698 to obtain a certifed copy. ONLY HARDCOPY RECORDS CERTIFIED BY THE GENERAL SECRETARY WILL BE DEEMED TO BE OFFICIAL.
TORONTO TRANSIT COMMISSION
REPORT NO.
MEETING DATE: August 27, 2003
SUBJECT: UNION SUBWAY STATION SECOND PLATFORM AND CONCOURSE IMPROVEMENTS
RECOMMENDATION
It is recommended that the Commission:
FUNDING
There are no funding implications to the TTC from the approval of the proposed layout of Union Subway Station. The Project is funded by the Toronto Waterfront Revitalization Corporation through funds provided by three levels of government (Transport Canada, Ontario Superbuild and City of Toronto).
BACKGROUND
Over the past fifty years, development of the downtown core has significantly increased, including the recent addition of two major stadiums (Skydome and Air Canada Centre). The existing TTC Union Subway Station concourse and platform (see attached Drawing No. 1) have limited capacity to carry highly concentrated passenger demands, which frequently exceed the practical and safe capacity of stairs, escalators and the platform during AM and PM peak periods and following the end of major events. Ongoing GO Transit expansion, Union Railway Station restoration and revitalization, planned redevelopment of the Portlands and continued development of Harbourfront will further strain the capacity of Union Subway Station.
In response to these pressures, TTC staff identified the need to expand the capacity of the existing station, both at the platform and concourse levels and to address layout and functional issues.
In early 2000, joint pedestrian counts were undertaken by GO Transit, the City of Toronto and TTC in order to forecast future volumes. In September 2000, the Commission authorized staff to commence preliminary design for the project. Subsequently, ArupNapa Canada was retained to complete a simulation of future pedestrian flows and to analyze station layout options prepared by TTC staff. The Steering Committee for the studies included representatives from GO Transit, City of Toronto and TTC.
The project was halted in June 2001 pending execution of funding agreements with the Toronto Waterfront Revitalization Corporation (TWRC). Work on the project has recommenced following the eventual execution of the agreement between TWRC and TTC in November 2002.
DISCUSSION
1. Project Objectives
The purpose of the Project is to achieve the following objectives:
2. Initial Screening
Preliminary functional plans were developed for the platform and concourse levels of the station. These plans underwent an evaluation and screening process to select the preferred station layout.
Options for expanding the platform level of the station are constrained by the foundations of the Royal Bank Building foundations to the north and by the prohibitive costs and operational impacts of attempting to widen the existing centre platform. The construction of a new platform to the south of the existing Finch Station-bound tracks was preferred because it was found to be both technically feasible and cost-effective.
For the concourse level of the station, five layouts (including the existing layout) were developed and evaluated. An initial screening of the five concourse layouts involved consideration of the results of forecast passenger volumes to 2021. Overall passenger volumes projected for 2021 were distributed to specific pedestrian corridors for each layout option based on a route choice analysis undertaken with input from City of Toronto, TTC and GO Transit staff. Options that did not include a west by-pass, all exhibited significant congestion at the entrance to Royal Bank Plaza. Accordingly, these options were eliminated from further consideration and a more refined analysis of Options 2 and 5 (see attached Drawing Nos. 2 and 3) was undertaken for AM peak and special events scenarios.
3. Pedestrian Simulations
The main differences between Options 2 and 5, which affected the results of the pedestrian simulations, are as follows:
Initial pedestrian simulations for Options 2 and 5 demonstrated that, due to future growth in demand, pedestrians would experience undesirable levels of service for both Options 2 and 5. Subsequently, Option 2 was refined further to increase the width of the west and east by-passes, thereby improving the station capacity.
Similarly, Option 5 was refined but even with widening, the ability to improve conditions in the central by-pass was limited due the conflicting movements between by-passing pedestrians moving north-south and TTC passengers moving east-west within the same area.
4. Comparison of Options 2 and 5 – Other Factors
The two options were also evaluated based on key project objectives, construction and maintenance costs, and disruption to electrical rooms, as summarized in Table 1.
5. Preferred Option
Based on the foregoing analyses, Option 2 is preferred because it fully achieves the TTC’s project objectives (i.e. separation of TTC passengers/ through pedestrians, consolidated fare paid area, no confusion for streetcar passengers at the concourse level). Pedestrian congestion issues can be addressed by increasing the width of the by-passes during the development of the station design.
6. Stakeholder and Public Consultation
TTC staff have undertaken a wide range of consultation initiatives for the project, including discussions with GO Transit and City of Toronto, presentations to affected property owners and special interest groups and a Public Open House, as described below.
7. Next Steps (see attached schedule)
Subject to Commission approval of the preferred option, as described above, the next steps for the Project are as follows:
JUSTIFICATION
Approval of the station preliminary concept is required to enable conceptual design to proceed on schedule and for the submission of required reports under the Canadian and Ontario Environmental Assessment Acts.
- - - - - - - - - - - -
August 13, 2003
50-SR
1054112
Attachments - Table 1 – Comparison of Options 2 and 5
- Drawing No. 1 - Existing Union Subway Station
- Drawing No. 2 - Option 2 (Preferred) - Concourse Level Plan
- Drawing No. 3 - Option 5 – Concourse Level Plan
- Project Schedule
Table 1
Comparison of Options 2 and 5
|
Criteria |
Option 2 |
Option 5 |
|
Separation of TTC Passengers and Through Pedestrians (separate paths improve pedestrians flows and avoid conflicts) |
Yes |
No |
|
Availability of Queuing Space at TTC Collectors Booth and Turnstiles (extra queuing space means shorter waiting times to pay fares and avoidance of conflicts with through pedestrians) |
Good |
Fair |
|
Ease of Streetcar Platform Access (split fare paid area at concourse results in fare paid access from east end of platform only) |
Good (Single fare paid area) |
Poor (Split fare paid area - similar to existing) |
|
Disruption to TTC Station Electrical Rooms (relocation results in station operations impacts and higher costs) |
No Relocation Required |
Relocation Required |
|
Area to Maintain (larger area means higher maintenance costs) |
1,700 square metres |
2,100 square metres |
|
Comparison of Capital Costs |
Lower than Option 5 |
Higher than Option 2 (due to expanded area and disruption to station electrical rooms) |