History and Major Milestones

Below is a Current List of the Project's Accomplishments to Date

2013

2012

2011

  • November 29, 2011: Tunnel Boring Machine "Yorkie" begins tunnelling operations (north tunnels).
  • November 2, 2011: Tunnel Boring Machine "Moley" begins tunnelling (south tunnels).
  • November 2, 2011; Contract awarded for A65-29 for Track Installation to Herzog/Delta, A Joint Venture.
  • September 8, 2011: Contract awarded for A31-1 for Steeles West Station to Walsh Construction Company Canada.
  • June 21, 2011: Contract awarded for A37-1 Vaughan Corporate Centre Subway Station to Carillion Construction Inc.
  • June 18, 2011: Tunnel Boring Machine "Holey" is readied for tunnelling (south tunnels).
  • June 17, 2011: Official Launch of Tunnel Boring for the Toronto-York Spadina Extension.
  • June 2, 2011: Contract awarded for A27-1 for Finch West Station to Bondfield Construction Co.
  • April 7, 2011: Contract awarded for A65-31 for Supply of Precast Concrete Double Ties and Elastomers to Munro Concrete.
  • January 19, 2011: Contract awarded for A35-26 for Highway 407 Station and the Northern Tunnels to OHL/FCC.

2010

 

2009

2008

2007

2006 

2005 

Note that this is not a comprehensive list of all contracts awarded for this Project.

AttentionService Alert:

Elevator Alert: Pape Station, westbound subway platform level to concourse to street, out of service.

Last updated 6:57 PM

Construction Activity Maps

Interactive Map

View the Construction Activity Maps that feature subway construction information in your neighbourhood.

Construction Activity Maps

Latest Project News

Read the latest Project News featuring a story about Vaughan Metropolitan Centre Station.

Project News April 2014

Photo Gallery

Check out the latest construction photos and project YouTube videos.

Click here to view the Photo Gallery.

About the Project