Elevators and Escalators
Planned Maintenance
Accessible Elevator Construction
The Toronto Transit Commission has an ongoing program to improve public accessibility. New information will be posted as it becomes available.
Union Station - Second Platform Project
The Lift at Union Station from street to concourse has been taken out of service as part of the start of construction for the Union Station Second Platform Project. These are the accessible alternatives for Union Station.
Lawrence West Station - Elevator Installation
Regular maintenance of TTC elevators and escalators keeps them working reliably and safely. To complete this important work, specific units will need to be out of service from time to time.
Following is a list of planned maintenance. Please note: Locations and schedules are subject to change without notice.
Elevators - Planned Maintenance
| Station | Elevator Location | Scheduled Start Date | Scheduled Completion Date |
|---|---|---|---|
| Eglinton West Station | Platform to Bus Loop | June 17, 2013 | June 21, 2013 |
Escalators - Planned Maintenance
| Station | Escalator Location | Scheduled Start Date | Scheduled Completion Date |
|---|---|---|---|
| Finch Station | Platform To Concourse | April 8, 2013 | August 8, 2013 |
| Lawrence Station | Bedford Park Automatic Entrance Concourse To Train Platform | May 10, 2013 | October 31, 2013 |
| Ossington Station | East End - Westbound Platform To Concourse | June 18, 2013 | June 21, 2013 |
| Islington Station | East End - Platform To Concourse | June 18, 2013 | June 21, 2013 |
| Kennedy Station | East Side Bus Level To Scarborough RT | June 17, 2013 | June 20, 2013 |
| Dundas Station | Underpass To Southbound And Atrium Entrance | June 17, 2013 | June 20, 2013 |
| Sheppard-Yonge Station | Concourse To Concourse | June 18, 2013 | June 21, 2013 |
| Wilson Station | Bus Platform Walkway To Upper Concourse | June 17, 2013 | June 20, 2013 |