This page includes information about construction projects which impact customer travel directly. For information about major construction projects, please visit projects.ttc.ca.

Learn about when and why TTC needs to complete overnight construction to keep transit moving.

Learn about the causes of subway noise and vibration and TTC’s work to address it.

Bus stop improvements

Bus stop construction will take up to a week, pending location, site and weather conditions.

Chester Station - station improvements

Scheduled for completion in 2021

Don Mills Station - bus transfer level ventilation upgrades

April 2017 to early 2019

Dundas West Station - roof rehabilitation

Starting as early as March 27, 2019

Dupont Station Easier Access Project

Lane reductions at Spadina Road and Dupont Street until the end of the project

Finch Station - Yonge/Hendon west stairway closure

April 15 to June 10

Glencairn Station - skylight replacement

August 2017 to December 2019

Greenwood Station Easier Access project land surveying

Starting as early as July 23, 2018

Greenwood Yard - concrete delivery

Scheduled for Thursday, March 21

Kennedy Station - Eglinton Crosstown construction

May 1, 2017 until approximately 2021

Kipling Station - Metrolinx construction impacts

Reduced parking and access changes at Kipling Station

Lawrence East Station - roof rehabilitation

Mid-April 2019 to Mid-January 2020

Line 1 Yonge Subway Extension - preliminary studies

Starting as early as March 4, 2019

Line 2 East Extension - Enbridge gas relocation work on Hollyhedge Drive at Danforth Road

Starting week of February 19, 2019

Line 2 East Extension - Enbridge gas relocation work on McCowan Road at St. Andrews Road

Starting April 1, 2019

Line 2 East Extension - Enbridge gas relocation work on Progress Avenue at Corporate Drive

Starting February 25, 2019

Line 2 East Extension - tree survey work from Eglinton Avenue East to Scarborough Town Centre

March 27 to June 2019

McCaul Street between Orde Street and Baldwin Street - preliminary rail welding work

Starting April 15 - in advance of City/TTC track replacement project on McCaul Street

McNicoll Bus Garage - emergency evacuation drill

Thursday, April 18, 2019 from 11:30 a.m. to 12 p.m.

McNicoll Bus Garage - weekend work

Starting September 30, 2017 and onwards - 9 a.m. to 5 p.m.

Relief Line South Study - Preliminary Field Testing at multiple locations

Ongoing testing along approved Relief Line South alignment

Roncesvalles Yard - modifications to track and carhouse

April 2, 2018 to Spring 2020

Royal York Station - bus loop closed for construction

May 7 to Spring 2019

Runnymede Station - Easier Access (Elevator) Project

Construction from late 2018 to late 2020

Spadina Road and Lowther Avenue - field testing

Continuing as early as February 4, 2019

Victoria Park to Warden stations - lighting upgrades

Ongoing overnight work required for safety

Wellesley Station - Easier Access project

Bus loop closed as of April 1, 2018 for elevator shaft construction

Wilson Station - elevator construction

Starting as early as November 7, 2018

Wilson Station - temporary closure of Tippet Road commuter lot

Additional commuter parking available at Spadina Subway Extension stations and Yorkdale Station

Yonge Street north of Carlton/College - subway ventilation shaft essential repairs

Starting April 22 for approximately eight weeks