Access Hubs

Formerly referred to as Mobility Transfer Hubs, Access Hubs will provide customers with a more comfortable place to wait when transferring between Wheel-Trans and other TTC vehicles. For many Wheel-Trans customers, weather and time-of day can have an impact on their ability to use conventional transit. The Access Hubs will be dry and well-lit; spacious enough for multiple mobility devices; have automatic doors and provide generous seating.

There will be 16 Hubs across the City and currently 14 are scheduled for construction in 11 key locations over the next several months. These hubs, which are partially funded by the Public Transit Infrastructure Fund, will support our Family of Services model, by making connections to conventional transit easier for Wheel-Trans customers.

What we are doing

As a part of the TTC’s ongoing Access Hub program, bus stops at select transfer points throughout the city are being upgraded to become more accessible.


Current construction locations - ongoing until Spring 2020

Don Mills and Freshmeadow

One Access Hub will be built at the North East corner of the Don Mills and Freshmeadow intersection.

The Access Hub will be 6 feet by 25 feet.

Work hours

The majority of work will take place between 7 a.m. and 11 p.m., as required. Some overnight and weekend work will be required during the course of this project in order to complete the work as quickly as possible

TTC Service

Full bus service will remain during the construction at the intersection.

The access hubs will serve these bus lines:

  • 51 – Leslie
  • 25 – Don Mills
  • 925 – Don Mills Express

Ellesmere and Victoria Park

Two Access Hubs will be built, one at the North-West corner and one at South-East corner of the Ellesmere and Victoria Park intersection.

The Access Hubs will be 10 feet by 25 feet.

Work hours

The majority of work will take place between 7 a.m. and 11 p.m., as required. Some overnight and weekend work will be required during the course of this project in order to complete the work as quickly as possible

TTC Service

Full bus service will remain during the construction at the intersection.

The access hubs will serve these bus lines:

  • 24 Victoria Park
  • 924 Victoria Park Express
  • 95 York Mills
  • 995 York Mills Express
  • 144 Downtown/Don Valley Express

Jane and Eglinton

Two Access Hubs will be built, one at the North-East corner and one at South-West corner of the Jane and Eglinton intersection.

The Access Hubs will be 10 feet by 25 feet.

Work hours

The majority of work will take place between 7 a.m. and 11 p.m., as required. Some overnight and weekend work will be required during the course of this project in order to complete the work as quickly as possible

TTC service

Full bus service will remain during the construction at the intersection.

The access hubs will serve these bus lines:

  • 35 Jane
  • 935 Jane Express
  • 32 Eglinton West

Kipling and Dixon

Two Access Hubs will be built, one at the North-West corner and one at South-West corner of the Kipling and Dixon intersection.

The Access Hubs will be 6 feet by 25 feet and 10 feet by 20 feet.

Work hours

The majority of work will take place between 7 a.m. and 11 p.m., as required. Some overnight and weekend work will be required during the course of this project in order to complete the work as quickly as possible.

TTC service

Full bus service will remain during the construction at the intersection.

The access hubs will serve these bus lines:

  • 45 – Kipling
  • 945 – Kipling Express
  • 52 – Lawrence West
  • 952 – Lawrence West Express
  • 111 – The East Mall

Long Branch

One Access Hub will be built at the Long Branch Loop (3830 Lake Shore Blvd W) starting as early as January 27, 2020.

The Access Hub will be 10 feet by 25 feet.

Work hours

The majority of work will take place between 7 a.m. and 11 p.m., as required. Some overnight and weekend work will be required during the course of this project in order to complete the work as quickly as possible

TTC Service

Full bus service will remain during the construction at the intersection.

The access hubs will serve these bus lines:

  • 123 – Sherway
  • 110 – Islington South
  • 501 – Queen

Neilson and Ellesmere 

Two Access Hubs will be built, one at the North East and South West corners of Neilson and Ellesmere.

The Access Hubs will be 6 feet by 25 feet (NE) and 10 feet by 20 feet (SW).

Work hours

The majority of work will take place between 7 a.m. and 11 p.m., as required. Some overnight and weekend work will be required during the course of this project in order to complete the work as quickly as possible.

TTC service

Full bus service will remain during the construction at the intersection.

The access hubs will serve these bus lines:

  • 38 – Highland Creek
  • 95 – York Mills
  • 133 – Neilson
  • 995 – York Mills Express

Victoria Park and Meadow 

One Access Hub will be built at Victoria Park and Meadow.

The Access Hub will be 7.5 by 16.5 feet.

Work activities and hours

  • Work activities started as early as December 16 and will take place in the public right-of-way.
  • The majority of work will take place between 7 a.m. and 7 p.m., as required.
  • No construction activities shall take place during hours of worship at Kingdom Hall.
  • Some overnight and weekend work may be required during the course of this project in order to complete the work as quickly as possible.

TTC service

The bus stop will be temporarily relocated north of the work zone for the duration of the construction.


Overlea and Thorncliffe 

Two Access Hubs will be built at Overlea and Thorncliffe (North West and South West corners).

The Access Hubs will be 10 feet by 25 feet.

Work hours

The majority of work will take place between 7 a.m. and 11 p.m., as required. Some overnight and weekend work will be required during the course of this project in order to complete the work as quickly as possible.

TTC service

Full bus service will remain during the construction at the intersection.

The access hubs will serve these bus lines:

  • 25 – Don Mills
  • 925 – Don Mills Express
  • 100 – Flemingdon Park
  • 81 – Thorncliffe Park

Yonge and Steeles

One Access Hub will be built at Yonge and Steeles.

The Access Hub will be 10 by 25 feet.

Work activities and hours

  • Work activities will start as early as January 17, 2019 and will take place in the public right-of-way.
  • The majority of work will take place between 7 a.m. and 7 p.m., as required.
  • Some overnight and weekend work may be required during the course of this project in order to complete the work as quickly as possible.
  • Construction vehicles will utilize a small portion of the corner of the parking lot at Centrepoint Mall.

TTC service

The bus stop will be temporarily relocated for the duration of the construction.


For further information:

Lema Salaymeh, Senior Community Liaison, Lema.Salaymeh@ttc.ca, (647) 529-4297